Daily Archives: July 25, 2013


Elevators 25 (1.25 hrs)

I back riveted the stiffeners to the left elevator and the trim reinforcement plate. I was also able to get started on the skeleton. Because this is a replacement skin, I plan to rivet the skeleton before final drilling the skin. My hope is to avoid any alignment deviation. The initial tolerances are so good I think all will be ok.

20130725-192136.jpg

20130725-192143.jpg

I did this in the correct order this time around!20130725-192148.jpg

20130725-192155.jpg

20130725-192201.jpg